Monday, August 10, 2009

Summer Time Porch Sittin

Ava and her best boyfriend Cade took a break from playing today to relax on the front porch swing. I caught em kissin!! Of course Cade didnt say no. Check out Cade sportin' his Marley shirt from St. John.




10702 Orlando Ready for Plumbing Inspection

Eddy's guys got the water lines installed today and ready for inspection. Once the slab is down, Chad and his guys will have a long way to travel across town to come and frame this house. Its all the way across the street from 4012 107th Street.





4012 107th Framing Started Today

My friend Chad and his crew started framing today. This is one of my favorite parts of the whole process. I first met Chad at a cookout that our church (St Lukes) was having @ 98th and Frankford back in the Spring of 2007. We hit it off and now he is one of my favorite guys to be around. He has been a great influence on me personally and professionally. He has a wealth of experience in the construction industry and this crazy thing we call LIFE.


CHAD


Saturday, August 8, 2009

10702 Orlando- Plumbing Started

The slab was formed up and the plumbers started the waste line rough in yesterday. Monday they will do the water lines and call for inspection Tuesday.



4012 107th Street- Slab Pour

Yesterday was a success getting the slab poured and finished out. Chad will start framing Monday.









Monday, August 3, 2009

4012 107th Street Slab Back Fill

Getting the slab ready for a Thursday pour. Chad is boucing off the walls ready to frame!!

10702 Orlando Footings Poured

Finally after 2 rain delays, the footing were poured today.