Wednesday, June 30, 2010

2011 Parade of Homes

Yesterday I was lucky enough to obtain a lot in the 2011 Parade of Homes in The Trails at Regal Park. This neighborhood will be located West of Iola on 90th Street. It is going to be a fantastic location for the premier location of the 2011 Parade. There will be some great homes built around a circular park and walking trail. I am working on plans already; hard to believe for a house that is 1 year away from being done. My lot faces West and is on a corner. I can't wait to get started on this house in October.

Saturday, June 19, 2010

9105 Hyden Moving Along

The house is completely painted and the electrical fixtures were installed yesterday.
Stop by this weekend and take a look.


4010 107th Roofing and Chimney

This house was roofed and the HVAC was roughed in this week. The roof was left off around the chimney area because we are going to install a stucco chimney. It gets a little messy up there while they are doing it. This picture also shows the huge side patio and yard that will be on the side of the house rather than a back yard. The home owner will be able to access the covered patio from three different doors within the house.
Next up: It will take 2 days next week to rough in the electrical and we will be sheetrocking shortly after that.


Thursday, June 10, 2010

10711 Norfolk- Orchard Park

Plans are being worked on for 10711 Norfolk Avenue. This home will be 3,000SF and will include, 3 bedrooms, 2.5 baths, basement and 3 car garage. This house will be a hybrid of a garden home and a traditional house being that it will only have a side yard but windows will be on both sides of the house. Turn North on Norfolk off 109th Street and you will see the location. It will have a great view and will be in the heart of Orchard Park. I should get going in mid July with the trenching of the basement.

4010 107th Street -Framing Complete

Some people have asked me how long it takes to frame a house this size(3450 SF). I have a great framing crew that got this house totally complete in 12 days. Keep in mind there was an average of 10 men on this house everyday except Memorial Day and Sundays. These guys work extremely hard even in the 100 degree heat. The house is dried-in with Titanium and ready for plumbing and electrical rough-in next week. Go by and take a look this weekend if you get a chance.







6306 77th Cabinets Started

The outside is complete. Trim and cabinets should be done by the end of next week.